Mecklenburg Tobacco Warehouse Completed Preservation Initiatives

 2002            – Clean-up and Emergency Stabilization                                  $10,800

(Corporation of Shepherdstown)

2005           – Repair and paint roof                                                                $  6,075

2006       – Manufacture and install window shutters                                   $  1,168

– Structural engineering analysis                                                       $  1,000

2007        – Stonework repair and repointing                                                  $27,843

– Stonework repair and repointing                                                   $  6,250

2010           – Historic Structures Report                                                        $  3,000

2011           – Demolition of interior walls and flooring                                  $  6,250

2012          – Demolition of bearing beams, disposal of interior debris

  and pipe fittings,  installation of exterior door                              $  5,000

– Repair and repointing of corbelled brick roof eaves                     $  2,640

– Excavate and repoint riverfront and west walls, and

install French drain and drainage stone.                                         $  5,000

 

Expenditures to date:

Corporation of Shepherdstown                                     $10,800

Friends of Shepherdstown Riverfront, Inc.                 $64,226